3M Telecom Systems Div. - Cabling Installation & Maintenance

3M Telecom Systems Div.


Aug 1, 1997

Dan Silver

To manage the planning and implementation of the Getty Center technology network in Los Angeles, CA, the organization brought in 26-year telecommunications industry veteran Dave Archer as senior telecommunications analyst. Working with a team of five specialists, Archer found a cost-effective solution that would meet all of Getty`s requirements for flexibility, upgradability, and future growth.

The scope of the project was defined by several parameters. Gigabit bandwidth was required to service a network of more than 2400 nodes. Telecommunications closet (tc) space was at a premium, so the system architecture had to consume as little floor space as possible. And the process of making changes to the network had to be fast, easy, and cost-effective.

In the spirit of this leading-edge facility, Archer`s team was challenged to find the best long-term technology solution. "We`re building a facility here to serve people for longer than the 50-year life span of normal business buildings," Archer explains.

The Getty Center network had to be designed for computers, printers, and similar devices, as well as videoconferencing. Due to the museum`s extraordinary security requirements, telephone and security systems were scheduled to have their own cabling plants and not be integrated into the computer network.

So Archer proposed that a fiber-based system be used to meet these needs. "When you need a combination of bandwidth with distance, fiber is the winner," says Archer. "While copper`s bandwidth is being pushed, it cannot go as far as fiber."

In the long run, fiber proved to be the most effective solution. Use of a centralized network administration architecture allowed the elimination of all of the electronics between the desktop and computer room, enabling the center to save space. There was no need for switches in tcs, which would have consumed 100 square feet per closet. With 55 tcs on site, the savings totaled $5 million, enough to cover the cost of the entire cabling system.

Fiber also enabled Getty Center to meet its flexibility requirements. Air-blown optical-fiber (abf) technology was selected for the cabling infrastructure. Because it can be installed in a fraction of the time it takes to pull conventional fiber cable, abf enables installers to set up new users or make changes in minutes, working from the central equipment room and at the desktop. Had the installation called for copper or conventional fiber technology, it would have required at least one additional full-time technician, resulting in higher costs.

Another factor in the decision for fiber was the center`s need to minimize downtime after its move. The staff had to be operational from day one, and the abf installation made that possible.

Archer believes that examining the big picture was the key to making the right decision, leading him to identify fiber as the most forward-thinking alternative. He convinced Getty`s management that the higher cost of fiber up front would be offset by not having to rewire the cabling plant later. "Our responsibility is to outfit the building with technology that will last as long as possible," he says. "Fiber optics is the medium of the future. If you can get to fiber now, it greatly reduces the trials and tribulations of conversions later on."

Click here to enlarge image

Senior telecommunications analyst Dave Archer decided to use a fiber-optic system at the Getty Center because it was cost-effective and would meet all of the institution`s requirements for flexibility, upgradability, and future growth.

Dan Silver is a market development manager for 3M Telecom Systems Div. (Austin, TX).


We Recommend

Skeletons in the telecom closet: The 10 scariest things I've seen this year

The 11 biggest cabling stories of 2011

Free app calculates loss budget

Reference poster dissects 802.11n

Fiber installation courses available online

Counterfeit cable exposed

Making the switch from 62.5- to 50-micron fiber

Telecom grounding and bonding standard published by NECA and BICSI

Free poster highlights 10 fiber-safety rules


Most Popular Articles
Top Blog Posts

TIA sets objectives for 40G over twisted pair

Cancer patients miss surgery due to cable theft

Cable tech finds 500-pound bear in customer’s basement

Nearly-electrocuted copper-cable thief speaks remorsefully

House explosions, captured on video, blamed on cable theft

Modified U.S. Army drone spies on WiFi users

Turn a wiring cabinet into a liquor cabinet


Receive Free E-mail Newsletters from Cabling Installation & Maintenance

Want to hear about more articles like this one? Sign up for our free email newsletters.



Email:

First Name:

Last Name:

Promo Code (optional):

Country:

Available Newsletters:
Cabling News

Data Centers Report

Contractor Report

 


Cabling Installation & Maintenance Topic and Resource Categories:

Data CentersCabling Standards
Network CableConnectivity Technologies
Network ProtocolsIP Convergence
WirelessDesign, Installation & Testing
Current IssueArchives
Cabling BlogBuyer's Guide