Q: Does the tia/eia-568a Commercial Building Telecommunications Cabling Standard allow me to bring the cable into the closet, punch it down on a wall-mounted 110 block, off the 110 block to the 110 connector on a rack-mounted patch panel, and then use a patch cord to connect to a hub? Or should I eliminate the wall-mounted 110 block and punch it down directly on the 110 connector on a rack-mounted patch panel? The first scenario seems more flexible.

Richard Tweet

State of Alaska

Anchorage, AK

A: The standard does allow such an approach, but it is not the best-performing solution. In fact, every time you add another piece of connecting hardware to the channel, performance is degraded. The answer depends on how good your channel needs to be. Trading some performance for better cable administration may work fine in your particular situation, but I am more cautious.

Since the Telecommunications Industry Association and Electronic Industries Alliance (Arlington, VA) "invented" Category 5 cable back in November 1991, we have learned a plethora of new terms, such as short-link resonance phenomena, propagation delay, delay skew, structural return loss, and the latest--alien crosstalk (see "Alien crosstalk mandates E.T.--extra testing," Cabling Product News, page 16). Alien crosstalk occurs between the conductor pairs in one cable with conductor pairs in an adjacent cable.

I remember a cartoon from the days of the asbestos scare: Two rats were using handheld hairdryers and the caption read, "Remember the good old days, when all we had to do was smoke cigarettes and drink booze?" Now the cartoon could be: One Category 5 link says to the other, "Remember the good old days, when all we had to worry about was attenuation and near-end crosstalk?" My point is, the surprises just keep coming. The cable in the wall continues to be required to meet additional parameters that were not in the standard when the cable came off the production line and was installed in buildings around the globe.


We Recommend

Skeletons in the telecom closet: The 10 scariest things I've seen this year

The 11 biggest cabling stories of 2011

Free app calculates loss budget

Reference poster dissects 802.11n

Fiber installation courses available online

Counterfeit cable exposed

Making the switch from 62.5- to 50-micron fiber

Telecom grounding and bonding standard published by NECA and BICSI

Free poster highlights 10 fiber-safety rules


Most Popular Articles
Top Blog Posts

TIA sets objectives for 40G over twisted pair

Cancer patients miss surgery due to cable theft

Cable tech finds 500-pound bear in customer’s basement

Nearly-electrocuted copper-cable thief speaks remorsefully

House explosions, captured on video, blamed on cable theft

Modified U.S. Army drone spies on WiFi users

Turn a wiring cabinet into a liquor cabinet


Receive Free E-mail Newsletters from Cabling Installation & Maintenance

Want to hear about more articles like this one? Sign up for our free email newsletters.



Email:

First Name:

Last Name:

Promo Code (optional):

Country:

Available Newsletters:
Cabling News

Data Centers Report

Contractor Report

 


Cabling Installation & Maintenance Topic and Resource Categories:

Data CentersCabling Standards
Network CableConnectivity Technologies
Network ProtocolsIP Convergence
WirelessDesign, Installation & Testing
Current IssueArchives
Cabling BlogBuyer's Guide