Step 4: Gathering Requirements

Aug. 15, 2013

When it is time to start gathering the requirements for the data center design, there are a few points to consider.

First of all, it is important to keep an eye on what the requirements will be once the data center actually goes live ; not on what the requirements are today. Each business unit should communicate their 3 to 5 year plan for growth -- IT should understand each equipment manufacturer’s roadmap for this time period. In addition, anything that will ultimately be virtualized, outsourced to a service provider or moved to the public cloud should not be included in the requirements.

The next step is to create a redundancy and dependency grid for each application and system. This is an excellent tool for ascertaining the size, space, step functions for expansion, tier classification(s) and dependencies required for each application and system. The grid can get rather large and complicated; but it will provide cost saving to the company in the long run by preventing over designing the data center. The redundancy and dependency grid can also help determine the growth of the data center and allow for a more modular approach to building the data center.

<< PREV123 4 567891011NEXT>>

Sponsored Recommendations

What you need to know about 6A cabling

Aug. 3, 2022
Did you know that Category 6A cable is the best choice for structured cabling?

Cat 6A Frequently Asked Questions

April 29, 2024
At CommScope we know about network change and the importance of getting it right. Conclusion Category 6A cabling and connectivity.

Cat 6A Hard Facts

Aug. 3, 2022
At CommScope we know about network change and the importance of getting it right. Conclusion Category 6A cabling and connectivity.

Why CommScope 6A?

Nov. 7, 2022
Inside buildings and across campuses, network demands and economics are changing. As applications like IoT, 10GBASE-T, multigigabit Wi-Fi 6/6E/7 and PoE++ become more common, ...